Summary
PL20160002727
Fiddlers Creek - Marco Shores - (DRI)
Pre-Application Meeting (Status: Submitted - Closed for Uploads)
Development Order Amendment (Status: Hearing Process - Open for Uploads)
Hearing Process - Open for Uploads
10/06/2016
FC COMMERCIAL LLC
DOA-(See scanned attached documents) RenaldPaul 08/09/2017 1:22 PM ******************************************* DRI - *Pre-App fees paid on PUDA- PL20160002496
Locations
Address
3120 Club Center BLVD

Address
3054 Sandpiper DR

Property
23899000023

Property
23899000049

Property
32432000345

Property
32432004024

Property
32432008208

Property
32432400521

Property
32432403900

Property
32432404501

Property
32433001165

Property
32433031960

Property
32433043026

Property
32433057025

Property
59430801105

Property
736640006

Property
736641005

Address
107 Creative DR

Application Types (Click to See Reviews)
Pre-Application Meeting
Submitted - Closed for Uploads
Development Order Amendment
Planning Commission & Board of Commissioners
Hearing Process - Open for Uploads
3 Re-Submittal (MINOR)      Status: Accepted
Review Application Type Outcome Est. Completion Completed
Addressing - GIS Review Development Order Amendment Approved 03/30/2018 03/28/2018
Annis Moxam ((239) 252-5519)   Send Email
Comprehensive Planning Review Development Order Amendment Approved 03/30/2018 03/20/2018
David C. Weeks ((239) 252-2306)   Send Email
Zoning Review Development Order Amendment Approved 03/30/2018 03/30/2018
Nancy Gundlach ((239) 252-2484)   Send Email
County Attorney Review Development Order Amendment Approved 03/30/2018 03/20/2018
Heidi Ashton-Cicko ((239) 252-8773)   Send Email
Miscellaneous Corrections
Resolved
03/20/2018

Miscellaneous Corrections: Please provide consent of owners that are affected by the master plan changes.
Miscellaneous Corrections
Resolved
03/20/2018

Miscellaneous Corrections: Is the entrance exhibit to be attached to the DRI resolution? Or is this only a visual aid for the hearing?
Miscellaneous Corrections
Resolved
03/20/2018

Miscellaneous Corrections: The draft resolution submitted by applicant states that the petitioner is 951 Land Holdings Ltd but the application states that the applicant is FCC Commercial LLC. Please advise which is the correct applicant or are they co-applicants.

2 Re-Submittal      Status: Returned for Correction
Review Application Type Outcome Est. Completion Completed
Addressing - GIS Review Development Order Amendment Approved 02/26/2018 02/15/2018
Annis Moxam ((239) 252-5519)   Send Email
Miscellaneous Corrections
Resolved
02/15/2018

On Master Plan – Exhibit FC – A1, please add street names Fiddlers Creek Parkway, Club Center Blvd, Marsh DR, Sandpiper DR and Championship DR.
Comprehensive Planning Review Development Order Amendment Approved 02/26/2018 02/26/2018
Marcia Kendall ((239) 252-2387)   Send Email
Miscellaneous Corrections
Resolved
02/26/2018

Based upon the above analysis, Comprehensive Planning staff finds the proposed amendment not consistent with the FLUE. However, the petition may be deemed consistent if the companion Growth Management Plan Amendment (GMPA) is adopted and becomes effective. The DOA needs to contain an effective date linked to the effective date of the companion GMPA.
Transportation Planning Review Development Order Amendment Approved 02/26/2018 02/27/2018
Michael Sawyer ((239) 252-2926)   Send Email
Additional Comments - Transportation Planning.
Resolved
02/27/2018

Additional Items that need to be addressed for Transportation Review: Rev.1: Copy of FDOT comments. 1.Below is a summary (included in page 1 of the enclosed pdf) of the proposed changes: •Create new map H and PUD master plan to reflect reallocation of commercial (B, Business) acreage to area on U.S. 41 near new project entrance (No new commercial square footage is proposed). •Revise map H and PUD master plan to better reflect as-built community plan and add new project accesses on U.S. 41. •Revise future golf course text in paragraphs D and H of the DRI D.O. 2.Modifications to access connections - there is master plan map dated March 8, 2017 (Exhibit FC-A1) on page 56 of the enclosed package. It is not clear how many new access points and/or changes are being requested to US 41. Additionally, it is not clear if this is to be the new Master Plan - an older map is included in page 110 of the pdf as Fiddler’s Creek Master Plan. 3.In order for FDOT to evaluate the local and regional impacts of the project change, the following analysis/information is necessary: •Traffic analysis is to be provided demonstrating that the new access points along US 41 will ensure a safe and efficient transportation movement. Map H is being revised, and the modification in access points has not been previously studied or reviewed. Hence, the applicant is to provide an analysis for the build-out as part of the NOPC to assess the impacts caused along the US 41 study intersections including project access points, pursuant to Section 380.06(19)(a), Florida Statutes (F.S.). •Provide clear revised Map H along with the originally approved Map H showing the new access points being requested. •The applicant is to provide a detailed status for the transportation conditions included in the DO. Enclosed is a page from the recent Annual Monitoring Report dated August 10, 2017 stating that “all required auxiliary lanes at each new intersection on US 41” is only 50% completed”. This is vague and non-specific to each intersection. Each intersection should be addressed.
Additional Comments - Transportation Planning.
Resolved
02/27/2018

Additional Items that need to be addressed for Transportation Review: Rev.1: Please see additional comments provided with the companion PUDA and GMPA petitions, address all cross over/related comments especially those additional FDOT and staff comments regarding proposed access changes.
Zoning Review Development Order Amendment Approved 02/26/2018 02/22/2018
Nancy Gundlach ((239) 252-2484)   Send Email
County Attorney Review Development Order Amendment Rejected 02/26/2018 02/26/2018
Heidi Ashton-Cicko ((239) 252-8773)   Send Email
Miscellaneous Corrections
Resolved
02/26/2018

Miscellaneous Corrections: Please email to me a word version of the Ordinance so that I can finalize it.
Miscellaneous Corrections
Carried Forward
03/16/2018

Miscellaneous Corrections: Please provide consent of owners that are affected by the master plan changes.
Miscellaneous Corrections
Carried Forward
03/16/2018

Miscellaneous Corrections: Is the entrance exhibit to be attached to the DRI resolution? Or is this only a visual aid for the hearing?
Miscellaneous Corrections
Carried Forward
03/16/2018

Miscellaneous Corrections: The draft resolution submitted by applicant states that the petitioner is 951 Land Holdings Ltd but the application states that the applicant is FCC Commercial LLC. Please advise which is the correct applicant or are they co-applicants.

1 Initial Submittal      Status: Returned for Correction
Review Application Type Outcome Est. Completion Completed
Addressing - GIS Review Development Order Amendment Rejected 09/13/2017 09/18/2017
Annis Moxam ((239) 252-5519)   Send Email
Miscellaneous Corrections
Carried Forward
01/26/2018

On Master Plan – Exhibit FC – A1, please add street names Fiddlers Creek Parkway, Club Center Blvd, Marsh DR, Sandpiper DR and Championship DR.
Comprehensive Planning Review Development Order Amendment Rejected 09/13/2017 09/22/2017
Sue Faulkner ((239) 252-5715)   Send Email
Miscellaneous Corrections
Carried Forward
01/26/2018

Based upon the above analysis, Comprehensive Planning staff finds the proposed amendment not consistent with the FLUE. However, the petition may be deemed consistent if the companion Growth Management Plan Amendment (GMPA) is adopted and becomes effective. The DOA needs to contain an effective date linked to the effective date of the companion GMPA.
Engineering Stormwater Review Development Order Amendment Approved 09/13/2017 10/16/2017
Richard Orth ((239) 252-5092)   Send Email
Miscellaneous Corrections
Withdrawn
10/16/2017

Miscellaneous Corrections: 1 Please identify on the Master Plan (Exhibit FC-A1) all existing and proposed drainage easements established to accommodate major off-site flows through the development.
Environmental Review Development Order Amendment Approved 09/13/2017 09/06/2017
Summer Araque ((239) 252-6290)   Send Email
Graphics - GIS Review Development Order Amendment Approved 09/13/2017 08/23/2017
Beth Yang ((239) 252-6208)   Send Email
Transportation Planning Review Development Order Amendment Rejected 09/13/2017 09/21/2017
Michael Sawyer ((239) 252-2926)   Send Email
Additional Comments - Transportation Planning.
Carried Forward
01/26/2018

Additional Items that need to be addressed for Transportation Review: Rev.1: Copy of FDOT comments. 1.Below is a summary (included in page 1 of the enclosed pdf) of the proposed changes: •Create new map H and PUD master plan to reflect reallocation of commercial (B, Business) acreage to area on U.S. 41 near new project entrance (No new commercial square footage is proposed). •Revise map H and PUD master plan to better reflect as-built community plan and add new project accesses on U.S. 41. •Revise future golf course text in paragraphs D and H of the DRI D.O. 2.Modifications to access connections - there is master plan map dated March 8, 2017 (Exhibit FC-A1) on page 56 of the enclosed package. It is not clear how many new access points and/or changes are being requested to US 41. Additionally, it is not clear if this is to be the new Master Plan - an older map is included in page 110 of the pdf as Fiddler’s Creek Master Plan. 3.In order for FDOT to evaluate the local and regional impacts of the project change, the following analysis/information is necessary: •Traffic analysis is to be provided demonstrating that the new access points along US 41 will ensure a safe and efficient transportation movement. Map H is being revised, and the modification in access points has not been previously studied or reviewed. Hence, the applicant is to provide an analysis for the build-out as part of the NOPC to assess the impacts caused along the US 41 study intersections including project access points, pursuant to Section 380.06(19)(a), Florida Statutes (F.S.). •Provide clear revised Map H along with the originally approved Map H showing the new access points being requested. •The applicant is to provide a detailed status for the transportation conditions included in the DO. Enclosed is a page from the recent Annual Monitoring Report dated August 10, 2017 stating that “all required auxiliary lanes at each new intersection on US 41” is only 50% completed”. This is vague and non-specific to each intersection. Each intersection should be addressed.
Additional Comments - Transportation Planning.
Carried Forward
01/26/2018

Additional Items that need to be addressed for Transportation Review: Rev.1: Please see additional comments provided with the companion PUDA and GMPA petitions, address all cross over/related comments especially those additional FDOT and staff comments regarding proposed access changes.
Zoning Review Development Order Amendment Approved 09/13/2017 10/11/2017
Nancy Gundlach ((239) 252-2484)   Send Email
County Attorney Review Development Order Amendment Rejected 09/13/2017 09/14/2017
Heidi Ashton-Cicko ((239) 252-8773)   Send Email
Miscellaneous Corrections
Carried Forward
01/26/2018

Miscellaneous Corrections: Please email to me a word version of the Ordinance so that I can finalize it.
Miscellaneous Corrections
Carried Forward
01/26/2018

Miscellaneous Corrections: See additional comments to be sent by email during the week of Sept. 18.
Public Utilities - PUED Review Development Order Amendment Approved 09/13/2017 09/11/2017
Eric Fey ((239) 252-2434)   Send Email

Fees
Paid Fees Amount Paid Owing Date Paid
Pre-application Meeting $500.00 $500.00 Paid 10/13/2016
Development Order, Amendment (FR) $6,000.00 $6,000.00 Paid 08/15/2017
Site Area (Acreage) fee $5,000.00 $5,000.00 Paid 08/15/2017
Fire Code Review - Development Order Amendment $120.00 $120.00 Paid 08/15/2017
Legal Advertising Fee $1,125.00 $1,125.00 Paid 08/15/2017
Legal Advertising Fee (BCC) $500.00 $500.00 Paid 08/15/2017
TIS Methodology Review $500.00 $500.00 Paid 08/15/2017
Comp Planning Review - DRI $2,250.00 $2,250.00 Paid 08/15/2017
Graphics Property Notification Address Listing $451.74 $451.74 Paid 11/21/2017
Property Owner Notifications $3,972.40 $3,972.40 Paid 04/04/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Your project will not be reviewed until all fees are paid in full.

Deposits & Bonds

There are no deposits or bonds for this planning application.

Inspections

There are no inspections for this planning application.

Documents & Images
Date Uploaded Document Name
10/06/2016 Addressing Checklist Approved
10/13/2016 PL Payment Slip
10/13/2016 Receipt for transaction: 2016-067549
10/13/2016 Pre-App Notes - DRI
08/07/2017 Submittal 1 App Exh 1 Disclosure List
08/16/2017 Cover Letter/Narrative Statement (Submittal 1 CoverLtr-DRIAmend-County 2017 - Prepared.pdf)
08/07/2017 Submittal 1 App Exh 4 Detail of Request
08/16/2017 Current Master Plan (Submittal 1 Exhibit FC-A1 (Approved Master Plan) - Prepared.pdf)
08/16/2017 Aerial Photographs (Submittal 1 Aerial Location Map - Prepared0.pdf)
08/07/2017 Submittal 1 App Exh 2 Folio Numbers
03/16/2018 Submittal 3 - Development Order
04/18/2018 Updated Master Plan (Submittal 3 Exhibit FC-A1 (Proposed Master Plan)-v4 - Prepared.pdf)
01/25/2018 Submittal 2 - Affidavit of all owners
08/07/2017 Submittal 1 GB Peninsula Conversion to FCC Veneta
08/07/2017 Submittal 1 FCC Commercial, LLC Name Change
01/25/2018 Submittal 2 - Application Form
08/07/2017 Submittal 1 App Exh 3 Legal Description
08/07/2017 Submittal 1 Resolution 2000-458 DO 2000-06
01/25/2018 Submittal 2 - Traffic Impact Study (TIS)
08/07/2017 Submittal 1 Exhibit FC-C1 Legal Description
08/16/2017 Warranty Deed/Proof of Ownership (Submittal 1 Deeds - Prepared.pdf)
08/07/2017 Submittal 1 State NOPC App
08/07/2017 Submittal 1 Environmental Supp 09-2016
08/09/2017 Incomplete Submittal Letter (INC)
08/10/2017 Submittal 1 Addressing Cklst
08/10/2017 PL Payment Slip
08/15/2017 Receipt for transaction: 2017-052200
08/15/2017 RLS 17-CPS-01707 SUBMITTAL 1- RLS
09/22/2017 Comp Planning Consistency Review1.pdf
10/11/2017 Review Comment Letter
10/11/2017 Review Comment Letter
11/20/2017 PL Payment Slip
11/21/2017 Receipt for transaction: 2017-074639
01/02/2018 NIM Notice_PL20160002618&PL20160002496.pdf
03/16/2018 Submittal 3 - Response Letter
02/27/2018 Updated Master Plan (Submittal 2 FCPUD-US 41 Entrance Exhibit-v1 - Prepared.pdf)
01/25/2018 Submittal 2 - NOPC App Response
01/25/2018 Submittal 2 - FDOT Response Email
01/29/2018 Submittal 2 - RLS
02/23/2018 DOA-PL2016-2727 Marco Shores-Fiddlers Creek DOA R2.docx
03/13/2018 Review Comment Letter
03/16/2018 Submittal 3 - Affidavit of Authorization/Evidence of Authority
03/20/2018 Submittal 3 - Email from Planner (Minor Review Time)
03/20/2018 DOA-PL2016-2727 Marco Shores-Fiddlers Creek DOA R3.docx
03/20/2018 Title - 031218 (PL20160002727) qgm revision.doc
03/20/2018 Title - 3.20.18.doc
03/27/2018 Property Owner Notification Letter
03/27/2018 Hearing Notice to Newspaper_CCPC
03/27/2018 Naples Daily News Ad Proof-1967384.pdf
04/03/2018 PL Payment Slip
04/03/2018 PL20160002727 Legal Advertising Reconciliation .pdf